Login
312 23rd Street-Brooklyn NY-"Tear Down & Build Up" Excavation and Foundation Work: March 20, 2008 to May 27, 2008
Advanced Search
RSS Feed for this Album View Slideshow

312 23rd Street-Brooklyn NY-"Tear Down & Build Up"

1. 312 23rd... 2. Asbestos... 3. Work done... 4. All the... 5. Excavation ... 6. Chez 311... 7. Brick,...

Random Image

IMG_2386

IMG_2386

Date: 05/22/2008 Views: 2

Excavation and Foundation Work: March 20, 2008 to May 27, 2008

Work starts "toute-suite" after our friendly neighborhood developer pulls building permits. Monaco Construction and NY Finest Excavation get to work. Should be two weeks of work on the excavation, then foundation pour. Let's see how the crew does.

As an end note, after over two months, we here at Chez 311 learned a few things. Most laborers are AOK. Some are idiots. Most just don't care. And a few, well they are down right bad people. While we did well with most of the the guys at Monaco (foundation work), NY Finest (excavation work) did not live up to their name (unless they are the "finest" at being the dumbest outfit in Brooklyn, complete cowboys). Hopefully our friendly neighborhood developer will find better excavation companies in the future. Good start, very bad finish. Good riddance!

Date: 03/20/2008
Size: 16 items (190 items total)
nextlast
Excavation begins and construction fence up: March 3, 2008

Album: Excavation begins and construction fence up: March 3, 2008

Permits pulled and crew on site. Construction fence up...on our property as agreed and initial excavation begins.

Date: 03/20/2008
Size: 18 items
Views: 28
Excavation Day 2, DOB and work stops: March 24, 2008

Album: Excavation Day 2, DOB and work stops: March 24, 2008

Well, we show up after Easter weekend to excavation in full force, DOB as well...then issues a Stop Work Order. Hmmm?

Date: 03/24/2008
Size: 9 items
Views: 13
Excavation Day 3, SWO Numer 2: March 27, 2008

Album: Excavation Day 3, SWO Numer 2: March 27, 2008

After Monday's SWO and lift, the crew was back. But, so was DOB...and a new SWO.

Date: 03/27/2008
Size: 10 items
Views: 34
One Month Later, Excavation Day 4 Begins: April 23, 2008

Album: One Month Later, Excavation Day 4 Begins: April 23, 2008

Finally the two Stop Work Orders are lifted and excavation and now shoring (?) begins a new.

Date: 04/23/2008
Size: 9 items
Views: 21
Excavation Day 5, a Footing is Poured: April 24, 2008

Album: Excavation Day 5, a Footing is Poured: April 24, 2008

We were both out for most of the day, so photos are sparce. Shoring up, footing poured.

Date: 04/24/2008
Size: 4 items
Views: 19
Excavation Day 6 and the Shoring of Our Yard: April 25, 2008

Album: Excavation Day 6 and the Shoring of Our Yard: April 25, 2008

More digging, but the bigger news was the shoring began on our side of the hole.

Date: 04/25/2008
Size: 8 items
Views: 17
Excavation Days 7-8: April 29-30, 2008

Album: Excavation Days 7-8: April 29-30, 2008

After a rainy Sunday and Monday, the crews had 2 solid days of digging, building and pouring.

Date: 04/30/2008
Size: 15 items
Views: 27
Excavation and Pour Days 9-15: May 01-May 09, 2008

Album: Excavation and Pour Days 9-15: May 01-May 09, 2008

Letting a week's worth of work (and photos) pile up in one gallery. Much work done and even a surprise as well.

Date: 05/09/2008
Size: 36 items
Views: 26
Excavation and Pour Day 16 + recon: May 14, 2008

Album: Excavation and Pour Day 16 + recon: May 14, 2008

A new week and a new day of work. More work against 312 23rd Street and a bit of recon for me.

Date: 05/14/2008
Size: 10 items
Views: 16
nextlast
Page: 1 2
Powered by Gallery v2.2